Projects

/Projects

Goodwine Grain Coop

This section is located on Lehigh Road (CH5) 100N from 1200E to US Rte. 45 in Ford County, Illinois. The work performed on this section consists of cold milling the existing pavement, resurfacing with hot mix asphalt level binder and surface course, laying aggregate shoulders Type B along the edge of the pavement on the mainline and at the intersections and doing all other necessary work to complete the section.

Ford County Highway

This section is located on Lehigh Road (CH5) 100N from 1200E to US Rte. 45 in Ford County, Illinois. The work performed on this section consists of cold milling the existing pavement, resurfacing with hot mix asphalt level binder and surface course, laying aggregate shoulders Type B along the edge of the pavement on the mainline and at the intersections and doing all other necessary work to complete the section.

Porter Ave Watseka

This project consists of an installation of a 24” concrete storm sewer on Porter Ave, in Watseka Il. The storm sewer trench was patched with 2” HMA Binder course and the entire roadway was milled and replaced with one lift of HMA Surface course.

I-57 at Paxton

This I-57 improvement project included milling existing HMA surface 3 ½” down to bare concrete, and replacing it with 2 ¼” of HMA binder and 1 ½” of HMA surface on the mainline and ramp pavement and the shoulders.  After milling the pavement was patched with Class A patches on the mainline and Class B [...]

Route 50/Route 30 Matteson, IL

The Rte. 50/Rte. 30 project in Matteson consisted of asphalt surface removal, pavement patching, resurfacing with hotmix asphalt surface course, concrete sidewalks, combination concrete curb and gutter construction , pavement markings and pedestrian signal installation. Back to Projects

Illinois Route 394

We performed asphalt patching, grinding and resurfacing on 5.94 miles on IL-394 from Steger Road to just south of Elmscourt Lane in Crete, Steger and Sauk Village. The Illinois Department of Transportation nominated us for an Asphalt Paving Award on this project. Back to Projects

Watseka Commercial Parking Lot

This project included stone base and asphalt paving of all roads and parking areas both on and off-site. We were instrumental in helping this business meet the grand opening date by increasing our production and focusing on the project schedule. Back to Projects

Illinois Interstate 57

We worked on 4.42 miles of I-57 in Iroquois Country between IL-116 and US 24. The entire section was milled down to the existing concrete and resurfaced with 4” of asphalt polymerized binder course and 1.5” of polymerized asphalt surface course. This project also included the removal of three sets of dual structures to be replaced with double [...]

Bridge Over Iroquois River

This project involved the total replacement of the existing bridge of Illinois Route 1 over the Iroquois River. The work included cofferdams, 38-foot piers and 350 feet of steel reinforced concrete superstructures, reconstruction of the roadway with hot-mix asphalt pavement and shoulders, aggregate shoulders and guardrail removal and replacement. The structure is a four-span PCC reinforced deck 355’ long [...]